The project began exceptionally well on Monday 20th October. We owe a great deal of thanks to Chris Poulton, whose extensive preparation work enabled the team to start shaping bunkers immediately on Day 1. His efforts made it possible to complete the 16th Hole within this phase, without his commitment, the volume of work achieved simply would not have been possible.

Across the first three weeks of November, Patrick Quinn (Shaper) completed 15 new and improved bunkers, along with several areas of mounding. He also filled in and remodelled sections of existing bunkers on holes 11, 12, 13, and 14. During his final week, Patrick focused on the 16th Hole, transforming the area with remarkable results: the former “pit” has now been filled, and four new bunkers have been shaped.

Each of the 19 bunkers requires drainage installation, liner placement, and turf blocking. Patrick’s team successfully completed these steps on 16 bunkers within the initial four-week schedule. The remaining three bunkers on the 16th were completed in week five, with the assistance of an additional labourer.

Throughout the project, our greenkeeping team has been essential. Their dedication has been key to delivering such an extensive programme within the timeframe.

What challenges have you faced?

Since mid-November, persistent wet weather has significantly slowed progress. Transporting materials around the course became increasingly difficult, and on some days work was greatly restricted.

We had an unfortunate incident on the 21st November with over 40 Cows from the neighbouring farm accessing the course, this caused wide spread damage to several greens and areas of the newly shaped 11th Hole, delaying our green staff from supporting the project work in the timeframe we would have liked. Two machinery breakdowns to both the tractor and digger caused some further delays and ultimately resulted in turf and topsoil deadlines being missed.

With these set backs, we entered December with the topsoil work on holes 13 and 16 still outstanding. With limited time remaining of Andy (P. Quinn Construction) on-site, we made the decision to hire a dumper with tyres not typically used on a golf course. Though not ideal, this was absolutely necessary: it allowed us to safely transport three times the volume of material per run vs. the tractor trailer, which had also tipped over several times due to the ground conditions.

This has enabled us to complete the topsoil work on both holes over the past week. However, the machinery has created some damage along the access route along holes 1, 13, 17, and 18. Andy has repaired, flattened and reshaped the reachable damaged areas before leaving on Saturday 13th December. Our team will then top-dress and seed these areas in the spring, ready for the golf season – we will also ensure safe walking routes are in place and GUR notices are displayed as required.

What work remains?

All 19 bunkers have been shaped and top-soiled. However, our in-house team have some areas to complete on the greenside bunkers on holes 12 and 13, as well as drainage work to two bunkers on holes 12 and 14. There is also more than 3,000 square metres of turf to be laid – so a significant amount still to do.

When will the holes re-open?

We hope you can recognise conditions have not been ideal in recent weeks, but the project is nearing completion and the holes will be progressively opened as soon as viable. Given the substantial investment of time, effort and funding, we want to ensure the surfaces are properly protected and prepared.

Although the 10th and 11th holes have been turfed, they are not quite ‘golf ready’ and need further attention from our team. Foot traffic on newly laid turf – at this stage would cause damage particularly on the Par 3 holes where these areas are most vulnerable.

Further updates will follow, but for now 10, 11, 12, 13, 14 & 16 will remain closed.

Hole 10

A huge thank you to the Members who helped lay turf!

01
01

Hole 11

A huge thank you to the Members who helped lay turf!

01
01

Hole 12

Work in Progress

01
01

Hole 13

Work in Progress

01
01

Hole 14

Work in Progress

01
01

Hole 16

Work in Progress